How long Seattle ADU permits actually take in 2025
The SDCI dashboard, our project ledger, and the three things that move median timeline from 14 weeks to 18.

What SDCI publishes
SDCI maintains a public Permit Performance Dashboard with intake-to-issuance medians by permit type. The 2024 median for new ADU/DADU permits hovered around 14 weeks, with a long tail driven by correction cycles.
Pre-Approved DADU plans bypass the architectural review portion entirely and typically issue in 6–8 weeks.
Where the time goes
Intake screening: 1–2 weeks. First plan-review cycle: 4–6 weeks. Correction response by applicant: 1–4 weeks (this is where projects stall). Second review: 3–4 weeks. Issuance: 1 week. Add 4–6 weeks if a SEPA threshold determination is required.
Tip 116 documents the formal process in detail.
Three things that compress the timeline
First: pre-application conferences before formal submittal. Free, and they catch issues that would otherwise show up as round-one corrections. Second: complete drawing sets — structural, energy, stormwater, and survey submitted together. Third: 48-hour correction response. Most stalls are applicant-side, not City-side.


