REPORT_2026 / Puget Sound

2026 Puget Sound ADU cost report
Real $/sqft by city · No $250 headlines

We pulled the closing costs on every ADU and major remodel Golden State permitted in the last 24 months and normalized them to per-square-foot ranges by city, build type, and finish tier. This is what construction actually costs in the Puget Sound right now — not the number a salesperson quotes you on a discovery call.

$/sqft by city — hard cost only

Ranges reflect mid-tier finishes on a typical 600–900 sqft DADU or a 1,200–1,800 sqft interior remodel. Add 14–22% for soft costs (design, permits, geotech, surveys).

CityCountyDetached ADUGarage Conv.Attached / AADUPermit + Tap FeesNotes
SeattleKing$330–$380$230–$300$285–$345$9k–$22kSDCI design review surcharge on larger lots; sewer cap fees in older neighborhoods.
BellevueKing$335–$380$235–$305$290–$350$11k–$26kLUC R-rated zoning slows review when lot coverage > 35%.
KirklandKing$330–$375$230–$295$285–$340$8k–$20kDADU encouraged; tree retention drives site work cost on sloped lots.
RedmondKing$330–$378$230–$298$285–$345$9k–$21kFaster review than Seattle; geotech often required east of 148th.
SammamishKing$340–$380$240–$305$290–$350$10k–$24kCritical-areas overlays add $4k–$12k in studies.
TacomaPierce$330–$360$220–$285$275–$330$6k–$15kLowest fee schedule on the I-5 corridor; sewer side-sewer rebuilds common.
PuyallupPierce$330–$358$215–$280$270–$325$5k–$13kSchool impact fees apply to net new bedrooms.
EverettSnohomish$330–$365$225–$290$278–$335$7k–$17kSnohomish PUD service upgrades 200A common on older lots.
LynnwoodSnohomish$330–$370$228–$292$280–$338$7k–$18kStormwater detention triggers above 2,000 sqft of new impervious.
OlympiaThurston$330–$355$215–$280$270–$325$5k–$13kThurston County wells/septic add scope on unincorporated parcels.

What actually moves the number

Lot access

Crane vs. all-hand framing swings detached ADU labor by $18–$35/sqft.

Foundation type

Stem wall vs. monolithic slab differs $9–$14/sqft; pin piles add $14k–$28k where required.

Sewer/water

Side-sewer reroute and meter upsize commonly $8k–$22k in Seattle and Tacoma.

Energy code (WSEC 2021)

Heat-pump + envelope upgrades add ~$6–$11/sqft over 2018 baseline.

Finish tier

Builder-grade vs. mid-tier finishes swings $22–$40/sqft on a 700 sqft DADU.

Design review

Discretionary review in Seattle/Bellevue adds 4–9 weeks of carry cost.

Methodology

  • Sample: 41 permitted Golden State projects closed 2023-08 → 2025-11 across King, Pierce, Snohomish, Thurston.
  • Hard costs only in $/sqft columns. Soft costs (design, permits, geotech, surveys, utility connection) shown separately.
  • Garage conversion $/sqft reflects net new conditioned area, not raw garage footprint.
  • All numbers exclude site demolition over $8k, retaining walls > 4 ft, and accessory site features (patios, fences, irrigation).

Press and researchers may cite this report freely with attribution to Golden State ADU Builders — 2026 Puget Sound ADU Cost Report. For the raw permit list, email office@golden-adu.com.

Want your specific number?

Run our calculator with your lot, or book a 30-minute call with a licensed builder to walk through your address.

PUGET_2026 / NUMBER

The 2026 cost report shows the region. Get the number for YOUR address — not the regional median.

Region medians are useful — until they're not. Your block, your soils, your access change the number 15-30%. We'll send the lot-specific PDF.

  • Lot-specific 2026 cost — not a regional median
  • Includes 3 named local comparables
  • Free 2-page PDF within 48h
Replies within 1 business day
WA Lic. GOLDNAB882L2Building since 2012

Report sourced from 47 builds we delivered or estimated in 2025-26.

Direct line · Golden State ADU(206) 555-0192
LEAD_01 / FREE_CONSULT

Send me my lot-specific 2026 number

Address + size target. PDF in 48h.

We reply within 1 business day. No spam, ever.

◇ No sales script · No spam · Your details stay with Leo