How long does an ADU permit really take in Seattle?
SDCI says 8–12 weeks but every builder I talk to says 6+ months. What is the real permit timeline?
Realistic SDCI timing for a DADU in 2026 is 18–28 weeks total from intake to issuance: 2–3 weeks intake, 8–14 weeks first review, 4–6 weeks for our corrections response, 3–5 weeks for the second review cycle. Pre-approved DADU plans cut that to 10–14 weeks. The 8–12 week SDCI quote refers only to the first review cycle, not the full round-trip. Plan your construction start at least 6 months after design kickoff.