Real ADU permit timelines across the Puget Sound
Our actual submission-to-issuance data for Seattle, Bellevue, Kirkland, Redmond, and Tacoma — what to expect and where projects stall.

Median timelines (last 24 months)
Seattle: 14 weeks median, 11–18 week range. Plan-review correction cycles add 2–3 weeks each.
Bellevue: 12 weeks median. Special Use Permits add 4–6 weeks.
Kirkland: 11 weeks median, the most predictable East-side jurisdiction.
Redmond: 12 weeks median, with stormwater review the most common stall point.
Tacoma: 9 weeks median, the fastest of the major Puget Sound jurisdictions.
How we shorten the timeline
Pre-application meetings before the formal submittal catch zoning issues that would otherwise show up in correction round one.
Complete drawing sets — including stormwater, structural, and energy compliance — submitted together rather than rolled in. Partial submittals trigger a full re-review.
Same-day correction responses. We have a permit specialist who turns corrections within 48 hours, not the 2–3 weeks that's typical.


