REF_4801 · Detached ADU · Shoreline, WA

Shoreline Modern Cottage

Single-story 800 sqft DADU in Shoreline's Richmond Beach — light-gauge steel rainscreen, hyper-heat mini-split, designed for Sound Transit Lynnwood Link commuters.

Type
Detached ADU
Sqft
800
Beds / Baths
1 / 1
Completed
Jul 2024
Duration
30 wks
Budget
$280,000
Shoreline Modern Cottage — Detached ADU in Shoreline, WA

01 / BRIEF

What the owner asked for

Shoreline's 2022 DADU code update (SMC 20.40.235) made DADUs administratively permitted with no design review under 800 sqft. We designed exactly to that threshold to skip the discretionary review window.

02 / CHALLENGE

What stood in the way

Lot was within a King County Aquifer Recharge Area, restricting infiltration depth and requiring a sealed conveyance from any new impervious surface.

03 / APPROACH

How we solved it

Specified a fully sealed roof-to-grade drain leader system tied into the existing storm main. Used IBHS Fortified-equivalent roof detailing (clipped underlayment, fully adhered membrane at eaves) for long-term weather resilience.

04 / OUTCOME

What got delivered

Permit in 8 weeks (administrative track), build in 22 weeks. Owners' adult son moved in; the family avoided $2,400/month rent.

SPEC_05 / FACTS

Project specification

Footprint
800 sqft single-story
Bedrooms / baths
1 / 1
Review track
Administrative (no DR)

SCHEDULE_06 / PHASES

30-week delivery

  1. 01
    Feasibility & design
    4–6 wks

    Site survey, zoning memo, schematic plans, owner review.

  2. 02
    Construction docs
    3–4 wks

    Structural, MEP, energy compliance, permit-ready set.

  3. 03
    Permit review
    8 wks

    City corrections, utility sign-offs, building permit issued.

  4. 04
    Site work + foundation
    3–4 wks

    Erosion control, excavation, footings, slab or stem wall.

  5. 05
    Framing + dry-in
    5–6 wks

    Floor, walls, roof, windows, weather-resistive barrier.

  6. 06
    MEP rough-in + insulation
    4–5 wks

    Plumbing, electrical, HVAC, blower-door prep.

  7. 07
    Finish + cabinetry
    6–8 wks

    Drywall, paint, flooring, cabinets, tile, fixtures.

  8. 08
    Inspections + handover
    1–2 wks

    Final inspections, punch-list, 22-week build closeout.

MATERIAL_07

Materials

  • Cladding
    Light-gauge steel rainscreen on 3/4" furring
  • Roof
    TPO single-ply with clipped underlayment at eaves

SYSTEM_08

Systems

  • Heating / cooling
    Mitsubishi MUZ-FS12NAH hyper-heat, 12K BTU
  • Water heating
    AO Smith HPTU-50, hybrid heat pump

PERMIT_09 / RECORD

Permits & compliance

  • Permit number
    Shoreline PB-24-100422
  • Stormwater
    Sealed conveyance to public main (ARA compliance)

METRIC_10 / OUTCOME

By the numbers

8 weeks
Permit review
$28,800
Rent avoided/yr

LESSON_11 / FIELD NOTES

What we'd repeat

  • Designing to 800 sqft exactly (vs. 825) opened the administrative permit track, saving 6+ weeks.
  • Sealed conveyance in ARA zones is non-negotiable — infiltration trenches will not pass review.
FAQ

Frequently asked

  • Can I tour a project like "Shoreline Modern Cottage"?

    Yes — we typically have 6–10 ADUs in framing or finish at any time across the Puget Sound, so we can usually arrange a site walk on a project at the same stage you're planning. For completed projects, tours depend on the current owner's availability and privacy preferences. Request a tour and we'll match you to the closest active or completed project that resembles "Shoreline Modern Cottage" in size, configuration, and AHJ.

    Go deeper: Shoreline ADU overview

  • What did this project actually cost?

    Each project page includes the all-in cost range for the size and configuration shown, scaled to 2026 prices. Actual contract value at time of build is confidential to the client, but the range we publish is anchored in real numbers from our bid archive — not aspirational pricing. For a tailored estimate against your lot, run our feasibility study or use the cost calculator.

    Go deeper: Read the Five hidden ADU costs that wreck Puget Sound budgets guide

  • How long did this project take?

    Most projects of this size and configuration run 9–14 months from contract to certificate of occupancy: 6–8 weeks of design, 8–16 weeks of permit, 18–26 weeks of construction. Schedule variance is driven by AHJ workload, owner selection pace, and field-discovered conditions during demo or excavation. We publish a Gantt at contract and update it weekly.

    Go deeper: Read the Eastside deck cost & permits: cedar, IPE, composite (2026) guide

  • Could you build "Shoreline Modern Cottage" again on my lot?

    Often yes — most of our projects are anchored on repeatable design DNA (envelope details, structural assemblies, MEP standard layouts) that adapt to different lot conditions with modest configuration changes. We'll review your lot's zoning, soils, and access to confirm fit. Where the original layout doesn't fit, we propose the closest workable adaptation that preserves the look you liked.

    Go deeper: Shoreline ADU overview

  • What inspections did "Shoreline Modern Cottage" go through?

    Standard Puget Sound ADU inspection sequence applied: footing, underfloor MEP, framing, plumbing rough, electrical rough, mechanical rough, insulation, drywall nailing, shower pan, gas piping, final building, final plumbing, final electrical, final mechanical, and final energy verification (blower-door ≤3 ACH50). All passed with no notable callbacks — typical for our builds because we run internal QA checklists at each milestone.

    Go deeper: Shoreline ADU permit timeline

PROJECT_SHORELINE MODERN COTTAGE

Want a build like "Shoreline Modern Cottage" on your lot? Get a real number.

We can share the exact scope, finishes and budget from this project — and tell you what the same build would cost on your address.

  • Same crews, same subs, same standards as "Shoreline Modern Cottage"
  • Free build-like-this feasibility on your address
  • Reply within one business day
Replies within 1 business day
WA Lic. GOLDESA747LZBuilding since 2012
Direct line · Golden State ADU(425) 642-4142

We reply within 1 business day. No spam, ever.

◇ No sales script · No spam · Your details stay with our team