REF_4939 · Detached ADU · Sammamish, WA

Sammamish Modern Farmhouse ADU

1,000 sqft modern farmhouse DADU on a 1-acre Sammamish Plateau lot — board-and-batten Hardie, blackened steel roof.

Type
Detached ADU
Sqft
1,000
Beds / Baths
2 / 2
Completed
Jan 2025
Duration
34 wks
Budget
$360,000
Sammamish Modern Farmhouse ADU — Detached ADU in Sammamish, WA

01 / BRIEF

What the owner asked for

Empty-nesters wanted a DADU for the primary home to be downsized into eventually, with the current main home becoming the rental. Required Sammamish SMC 21A.30.305 compliance and on-site septic verification.

02 / CHALLENGE

What stood in the way

On-site septic system was 2003-vintage and sized for the existing 3-bed/2-bath home only. Adding 2 bedrooms triggered a Health Dept review.

03 / APPROACH

How we solved it

Worked with King County Public Health to upsize the septic (added 250-gallon polylock chamber + 80 LF of new drainfield).

04 / OUTCOME

What got delivered

Permit in 14 weeks (incl. septic review), build in 20 weeks. Long-term plan is to rent the main house in 2026.

SPEC_05 / FACTS

Project specification

Footprint
1,000 sqft single-story
Bedrooms / baths
2 / 2
Septic
Existing + 250 gal + 80 LF drainfield

SCHEDULE_06 / PHASES

34-week delivery

  1. 01
    Feasibility & design
    4–6 wks

    Site survey, zoning memo, schematic plans, owner review.

  2. 02
    Construction docs
    3–4 wks

    Structural, MEP, energy compliance, permit-ready set.

  3. 03
    Permit review
    14 wks

    City corrections, utility sign-offs, building permit issued.

  4. 04
    Site work + foundation
    3–4 wks

    Erosion control, excavation, footings, slab or stem wall.

  5. 05
    Framing + dry-in
    5–6 wks

    Floor, walls, roof, windows, weather-resistive barrier.

  6. 06
    MEP rough-in + insulation
    4–5 wks

    Plumbing, electrical, HVAC, blower-door prep.

  7. 07
    Finish + cabinetry
    6–8 wks

    Drywall, paint, flooring, cabinets, tile, fixtures.

  8. 08
    Inspections + handover
    1–2 wks

    Final inspections, punch-list, 20-week build closeout.

MATERIAL_07

Materials

  • Cladding
    Hardie board-and-batten, BM Simply White
  • Roof
    Standing seam 24-ga, matte black

SYSTEM_08

Systems

  • Heating / cooling
    Ducted Daikin Fit 24K BTU

PERMIT_09 / RECORD

Permits & compliance

  • Permit number
    Sammamish PR2024-0612
  • Septic review
    KC Health SE24-1188 (approved)

METRIC_10 / OUTCOME

By the numbers

+2 bedrooms equivalent
Septic capacity added

LESSON_11 / FIELD NOTES

What we'd repeat

  • On septic lots, always pull the original septic record (KC Health) before sizing the ADU — septic upsizes can add 3–8 weeks and $12–35K.
FAQ

Frequently asked

  • Can I tour a project like "Sammamish Modern Farmhouse ADU"?

    Yes — we typically have 6–10 ADUs in framing or finish at any time across the Puget Sound, so we can usually arrange a site walk on a project at the same stage you're planning. For completed projects, tours depend on the current owner's availability and privacy preferences. Request a tour and we'll match you to the closest active or completed project that resembles "Sammamish Modern Farmhouse ADU" in size, configuration, and AHJ.

    Go deeper: Sammamish ADU overview

  • What did this project actually cost?

    Each project page includes the all-in cost range for the size and configuration shown, scaled to 2026 prices. Actual contract value at time of build is confidential to the client, but the range we publish is anchored in real numbers from our bid archive — not aspirational pricing. For a tailored estimate against your lot, run our feasibility study or use the cost calculator.

    Go deeper: Read the Five hidden ADU costs that wreck Puget Sound budgets guide

  • How long did this project take?

    Most projects of this size and configuration run 9–14 months from contract to certificate of occupancy: 6–8 weeks of design, 8–16 weeks of permit, 18–26 weeks of construction. Schedule variance is driven by AHJ workload, owner selection pace, and field-discovered conditions during demo or excavation. We publish a Gantt at contract and update it weekly.

    Go deeper: Read the Eastside deck cost & permits: cedar, IPE, composite (2026) guide

  • Could you build "Sammamish Modern Farmhouse ADU" again on my lot?

    Often yes — most of our projects are anchored on repeatable design DNA (envelope details, structural assemblies, MEP standard layouts) that adapt to different lot conditions with modest configuration changes. We'll review your lot's zoning, soils, and access to confirm fit. Where the original layout doesn't fit, we propose the closest workable adaptation that preserves the look you liked.

    Go deeper: Sammamish ADU overview

  • What inspections did "Sammamish Modern Farmhouse ADU" go through?

    Standard Puget Sound ADU inspection sequence applied: footing, underfloor MEP, framing, plumbing rough, electrical rough, mechanical rough, insulation, drywall nailing, shower pan, gas piping, final building, final plumbing, final electrical, final mechanical, and final energy verification (blower-door ≤3 ACH50). All passed with no notable callbacks — typical for our builds because we run internal QA checklists at each milestone.

    Go deeper: Sammamish ADU permit timeline

PROJECT_SAMMAMISH MODERN FARMHOUSE ADU

Want a build like "Sammamish Modern Farmhouse Adu" on your lot? Get a real number.

We can share the exact scope, finishes and budget from this project — and tell you what the same build would cost on your address.

  • Same crews, same subs, same standards as "Sammamish Modern Farmhouse Adu"
  • Free build-like-this feasibility on your address
  • Reply within one business day
Replies within 1 business day
WA Lic. GOLDESA747LZBuilding since 2012
Direct line · Golden State ADU(425) 642-4142

We reply within 1 business day. No spam, ever.

◇ No sales script · No spam · Your details stay with our team