REF_4888 · Custom Addition · Renton, WA

Renton Rambler Addition

620 sqft single-story master suite + great-room addition on a 1971 rambler — Renton Highlands.

Type
Custom Addition
Sqft
620
Beds / Baths
1 / 1
Completed
Oct 2024
Duration
24 wks
Budget
$218,000
Renton Rambler Addition — Custom Addition in Renton, WA

01 / BRIEF

What the owner asked for

Owners wanted to age in place without stairs. Added a wheelchair-accessible master suite + great-room without compromising the original carport.

02 / CHALLENGE

What stood in the way

Existing rafters were 2x6 at 24" o.c. — insufficient to support a new flat-roof transition with PV panels. Required full structural rework of the existing roof tie-in.

03 / APPROACH

How we solved it

Sistered 2x10 rafters to existing 2x6s at the addition tie-in, then added a glulam ridge to support 5.4 kW of LG Neon PV.

04 / OUTCOME

What got delivered

Construction in 16 weeks after 8-week permit. Owners hosted Thanksgiving 2024 in the new great room.

SPEC_05 / FACTS

Project specification

Footprint
620 sqft single-story
Accessibility
ADA-compliant turning radius, roll-in shower

SCHEDULE_06 / PHASES

24-week delivery

  1. 01
    Feasibility & design
    4–6 wks

    Site survey, zoning memo, schematic plans, owner review.

  2. 02
    Construction docs
    3–4 wks

    Structural, MEP, energy compliance, permit-ready set.

  3. 03
    Permit review
    8 wks

    City corrections, utility sign-offs, building permit issued.

  4. 04
    Site work + foundation
    3–4 wks

    Erosion control, excavation, footings, slab or stem wall.

  5. 05
    Framing + dry-in
    5–6 wks

    Floor, walls, roof, windows, weather-resistive barrier.

  6. 06
    MEP rough-in + insulation
    4–5 wks

    Plumbing, electrical, HVAC, blower-door prep.

  7. 07
    Finish + cabinetry
    6–8 wks

    Drywall, paint, flooring, cabinets, tile, fixtures.

  8. 08
    Inspections + handover
    1–2 wks

    Final inspections, punch-list, 16-week build closeout.

MATERIAL_07

Materials

  • Floor
    Engineered white oak 7.5" plank
  • Roof
    TPO single-ply with PV-ready penetration grid

SYSTEM_08

Systems

  • Solar
    5.4 kW LG Neon R, Enphase IQ8M micros
  • Heating
    Existing forced air extended + radiant in bath

PERMIT_09 / RECORD

Permits & compliance

  • Permit number
    Renton B24-002188

METRIC_10 / OUTCOME

By the numbers

5.4 kW
PV system
~6,100 kWh
Annual PV offset

LESSON_11 / FIELD NOTES

What we'd repeat

  • Always check existing rafter capacity before promising a flat-roof addition over a stick-framed rambler.
FAQ

Frequently asked

  • Can I tour a project like "Renton Rambler Addition"?

    Yes — we typically have 6–10 ADUs in framing or finish at any time across the Puget Sound, so we can usually arrange a site walk on a project at the same stage you're planning. For completed projects, tours depend on the current owner's availability and privacy preferences. Request a tour and we'll match you to the closest active or completed project that resembles "Renton Rambler Addition" in size, configuration, and AHJ.

    Go deeper: Renton ADU overview

  • What did this project actually cost?

    Each project page includes the all-in cost range for the size and configuration shown, scaled to 2026 prices. Actual contract value at time of build is confidential to the client, but the range we publish is anchored in real numbers from our bid archive — not aspirational pricing. For a tailored estimate against your lot, run our feasibility study or use the cost calculator.

    Go deeper: Read the Five hidden ADU costs that wreck Puget Sound budgets guide

  • How long did this project take?

    Most projects of this size and configuration run 9–14 months from contract to certificate of occupancy: 6–8 weeks of design, 8–16 weeks of permit, 18–26 weeks of construction. Schedule variance is driven by AHJ workload, owner selection pace, and field-discovered conditions during demo or excavation. We publish a Gantt at contract and update it weekly.

    Go deeper: Read the Eastside deck cost & permits: cedar, IPE, composite (2026) guide

  • Could you build "Renton Rambler Addition" again on my lot?

    Often yes — most of our projects are anchored on repeatable design DNA (envelope details, structural assemblies, MEP standard layouts) that adapt to different lot conditions with modest configuration changes. We'll review your lot's zoning, soils, and access to confirm fit. Where the original layout doesn't fit, we propose the closest workable adaptation that preserves the look you liked.

    Go deeper: Renton ADU zoning lookup

  • What inspections did "Renton Rambler Addition" go through?

    Standard Puget Sound ADU inspection sequence applied: footing, underfloor MEP, framing, plumbing rough, electrical rough, mechanical rough, insulation, drywall nailing, shower pan, gas piping, final building, final plumbing, final electrical, final mechanical, and final energy verification (blower-door ≤3 ACH50). All passed with no notable callbacks — typical for our builds because we run internal QA checklists at each milestone.

    Go deeper: Renton ADU permit timeline

PROJECT_RENTON RAMBLER ADDITION

Want a build like "Renton Rambler Addition" on your lot? Get a real number.

We can share the exact scope, finishes and budget from this project — and tell you what the same build would cost on your address.

  • Same crews, same subs, same standards as "Renton Rambler Addition"
  • Free build-like-this feasibility on your address
  • Reply within one business day
Replies within 1 business day
WA Lic. GOLDESA747LZBuilding since 2012
Direct line · Golden State ADU(425) 642-4142