Mercer Island Interior
Open-plan kitchen + living addition with polished concrete floors and a 12'x4' fixed skylight — Mercer Island's First Hill.
- Type
- Custom Addition
- Sqft
- 850
- Beds / Baths
- 0 / 1
- Completed
- May 2024
- Duration
- 30 wks
- Budget
- $298,000

01 / BRIEF
What the owner asked for
Owners of a 1978 split-level wanted to convert the cramped dining-into-kitchen sequence into a single great room, with a new master suite stacked above. Mercer Island Code 19.02 caps lot coverage at 40% — the existing footprint was at 38%, leaving 240 sqft of horizontal expansion before triggering a variance.
02 / CHALLENGE
What stood in the way
Removing the existing kitchen's load-bearing wall meant introducing a 26' flush LVL beam, with point loads needing transfer through two stories down to a new pier in the crawl space.
03 / APPROACH
How we solved it
RDH Structural designed a triple 1-3/4" x 14" LVL with custom Simpson HUS columns at each bearing point. We used radiant in-slab heat (Uponor 1/2" PEX-A on 9" centers) in the new polished concrete and matched it to the existing perimeter baseboard with a 4-zone Taco SR504-EXP controller.
04 / OUTCOME
What got delivered
Permit in 11 weeks, build in 19 weeks. Project carried zero shoring change-orders. Appraisal post-completion came in at $284K above project cost.
SPEC_05 / FACTS
Project specification
- New footprint
- 240 sqft (horizontal) + 600 sqft (vertical)
- Total addition
- 850 sqft
- Ceiling height
- 10'-6" living, 9'-0" master
SCHEDULE_06 / PHASES
30-week delivery
- 01Feasibility & design4–6 wks
Site survey, zoning memo, schematic plans, owner review.
- 02Construction docs3–4 wks
Structural, MEP, energy compliance, permit-ready set.
- 03Permit review11 wks
City corrections, utility sign-offs, building permit issued.
- 04Site work + foundation3–4 wks
Erosion control, excavation, footings, slab or stem wall.
- 05Framing + dry-in5–6 wks
Floor, walls, roof, windows, weather-resistive barrier.
- 06MEP rough-in + insulation4–5 wks
Plumbing, electrical, HVAC, blower-door prep.
- 07Finish + cabinetry6–8 wks
Drywall, paint, flooring, cabinets, tile, fixtures.
- 08Inspections + handover1–2 wks
Final inspections, punch-list, 19-week build closeout.
MATERIAL_07
Materials
- FloorPolished concrete with hydronic radiant, 4" slab
- BeamTriple 1-3/4" x 14" LVL, Simpson HUS columns
- WindowsMarvin Essential, ultrex, U-0.28
SYSTEM_08
Systems
- Heating / coolingExisting forced air + new hydronic radiant
- SkylightVelux FCM 4622, 12'-0" x 4'-0" fixed laminated
- KitchenWolf 36" DF range, Sub-Zero 36" column refrigerator
PERMIT_09 / RECORD
Permits & compliance
- Permit numberMercer Island BLD24-0319
- Structural reviewEngineer-stamped per IBC §1604
METRIC_10 / OUTCOME
By the numbers
- +$284,000
- Reassessment delta
- Ff 35 / Fl 25
- Slab flatness
- 39.4%
- Lot coverage post-build
LESSON_11 / FIELD NOTES
What we'd repeat
- On Mercer Island, getting the lot coverage calc letter-perfect with the city before CDs saves a guaranteed correction cycle.
- Hydronic radiant in polished slab costs roughly $11/sqft more than baseboard but it's the only system that doesn't conflict with a great-room ceiling plan.
ARCHIVE_∞ / MORE
Other field reports
- REF_4492 · Detached ADUBallard Monolith
A 1,000 sqft two-story DADU clad in vertical western red cedar with floor-to-ceiling industrial glazing — long-term rental on a 4,800 sqft Ballard lot.
- REF_4376 · Attached ADUBellevue Wing
A 720 sqft side-yard AADU grafted onto a 1962 craftsman in West Bellevue — independent entry, separate utilities, no shared interior wall openings.
- REF_4218 · Garage ConversionKirkland Garage Studio
A two-car detached garage converted into a high-end work-from-home studio with a 6'x6' fixed skylight — Kirkland's Norkirk neighborhood.
Frequently asked
Can I tour a project like "Mercer Island Interior"?
Yes — we typically have 6–10 ADUs in framing or finish at any time across the Puget Sound, so we can usually arrange a site walk on a project at the same stage you're planning. For completed projects, tours depend on the current owner's availability and privacy preferences. Request a tour and we'll match you to the closest active or completed project that resembles "Mercer Island Interior" in size, configuration, and AHJ.
Go deeper: Read the Eastside deck cost & permits: cedar, IPE, composite (2026) guide
What did this project actually cost?
Each project page includes the all-in cost range for the size and configuration shown, scaled to 2026 prices. Actual contract value at time of build is confidential to the client, but the range we publish is anchored in real numbers from our bid archive — not aspirational pricing. For a tailored estimate against your lot, run our feasibility study or use the cost calculator.
Go deeper: Read the Five hidden ADU costs that wreck Puget Sound budgets guide
How long did this project take?
Most projects of this size and configuration run 9–14 months from contract to certificate of occupancy: 6–8 weeks of design, 8–16 weeks of permit, 18–26 weeks of construction. Schedule variance is driven by AHJ workload, owner selection pace, and field-discovered conditions during demo or excavation. We publish a Gantt at contract and update it weekly.
Go deeper: Read the Eastside deck cost & permits: cedar, IPE, composite (2026) guide
Could you build "Mercer Island Interior" again on my lot?
Often yes — most of our projects are anchored on repeatable design DNA (envelope details, structural assemblies, MEP standard layouts) that adapt to different lot conditions with modest configuration changes. We'll review your lot's zoning, soils, and access to confirm fit. Where the original layout doesn't fit, we propose the closest workable adaptation that preserves the look you liked.
Go deeper: Read the Eastside deck cost & permits: cedar, IPE, composite (2026) guide
What inspections did "Mercer Island Interior" go through?
Standard Puget Sound ADU inspection sequence applied: footing, underfloor MEP, framing, plumbing rough, electrical rough, mechanical rough, insulation, drywall nailing, shower pan, gas piping, final building, final plumbing, final electrical, final mechanical, and final energy verification (blower-door ≤3 ACH50). All passed with no notable callbacks — typical for our builds because we run internal QA checklists at each milestone.