REF_4855 · Detached ADU · Issaquah, WA

Issaquah Hillside DADU

Two-story DADU on a 22% sloped lot in Issaquah Highlands — engineered piers, cable-rail deck, panoramic Lake Sammamish view.

Type
Detached ADU
Sqft
950
Beds / Baths
2 / 1
Completed
Nov 2024
Duration
38 wks
Budget
$332,000
Issaquah Hillside DADU — Detached ADU in Issaquah, WA

01 / BRIEF

What the owner asked for

Owners wanted to capture lake views from a buildable backyard envelope on a heavily sloped Issaquah Highlands lot. IMC 18.07 requires geotech review for any structure on slopes >15%.

02 / CHALLENGE

What stood in the way

Slope, view corridors restricted by HOA CC&Rs, and a 30-foot stream buffer running along the south edge of the lot.

03 / APPROACH

How we solved it

Helical pier foundation (Magnum MH150, 9 piers) eliminated cut/fill and protected the stream buffer. Building was rotated 14° off the property line to align with view corridor while staying within HOA envelope.

04 / OUTCOME

What got delivered

Permit in 16 weeks (geotech + critical areas review), build in 22 weeks. Owners' parents moved in for winter 2024–25.

SPEC_05 / FACTS

Project specification

Footprint
475 sqft (two-story)
Bedrooms / baths
2 / 1
Foundation
9 helical piers, Magnum MH150

SCHEDULE_06 / PHASES

38-week delivery

  1. 01
    Feasibility & design
    4–6 wks

    Site survey, zoning memo, schematic plans, owner review.

  2. 02
    Construction docs
    3–4 wks

    Structural, MEP, energy compliance, permit-ready set.

  3. 03
    Permit review
    16 wks

    City corrections, utility sign-offs, building permit issued.

  4. 04
    Site work + foundation
    3–4 wks

    Erosion control, excavation, footings, slab or stem wall.

  5. 05
    Framing + dry-in
    5–6 wks

    Floor, walls, roof, windows, weather-resistive barrier.

  6. 06
    MEP rough-in + insulation
    4–5 wks

    Plumbing, electrical, HVAC, blower-door prep.

  7. 07
    Finish + cabinetry
    6–8 wks

    Drywall, paint, flooring, cabinets, tile, fixtures.

  8. 08
    Inspections + handover
    1–2 wks

    Final inspections, punch-list, 22-week build closeout.

MATERIAL_07

Materials

  • Cladding
    Kebony pine rainscreen, 1x6 horizontal
  • Deck rail
    AGS Stainless Clearview cable rail

SYSTEM_08

Systems

  • Heating / cooling
    Daikin Aurora 18K BTU multi-zone hyper-heat

PERMIT_09 / RECORD

Permits & compliance

  • Permit number
    Issaquah B24-0455
  • Geotech
    Earth Solutions NW report ESNW-24-119
  • Critical Areas
    Stream buffer mitigation plan approved

METRIC_10 / OUTCOME

By the numbers

9
Helical piers
0 cu yd
Cut/fill

LESSON_11 / FIELD NOTES

What we'd repeat

  • Helical piers cost ~$28K more than a conventional foundation but on >20% slopes they often save 4–6 weeks of excavation and shoring.
FAQ

Frequently asked

  • Can I tour a project like "Issaquah Hillside DADU"?

    Yes — we typically have 6–10 ADUs in framing or finish at any time across the Puget Sound, so we can usually arrange a site walk on a project at the same stage you're planning. For completed projects, tours depend on the current owner's availability and privacy preferences. Request a tour and we'll match you to the closest active or completed project that resembles "Issaquah Hillside DADU" in size, configuration, and AHJ.

    Go deeper: Issaquah ADU overview

  • What did this project actually cost?

    Each project page includes the all-in cost range for the size and configuration shown, scaled to 2026 prices. Actual contract value at time of build is confidential to the client, but the range we publish is anchored in real numbers from our bid archive — not aspirational pricing. For a tailored estimate against your lot, run our feasibility study or use the cost calculator.

    Go deeper: Read the Five hidden ADU costs that wreck Puget Sound budgets guide

  • How long did this project take?

    Most projects of this size and configuration run 9–14 months from contract to certificate of occupancy: 6–8 weeks of design, 8–16 weeks of permit, 18–26 weeks of construction. Schedule variance is driven by AHJ workload, owner selection pace, and field-discovered conditions during demo or excavation. We publish a Gantt at contract and update it weekly.

    Go deeper: Read the Eastside deck cost & permits: cedar, IPE, composite (2026) guide

  • Could you build "Issaquah Hillside DADU" again on my lot?

    Often yes — most of our projects are anchored on repeatable design DNA (envelope details, structural assemblies, MEP standard layouts) that adapt to different lot conditions with modest configuration changes. We'll review your lot's zoning, soils, and access to confirm fit. Where the original layout doesn't fit, we propose the closest workable adaptation that preserves the look you liked.

    Go deeper: Issaquah ADU overview

  • What inspections did "Issaquah Hillside DADU" go through?

    Standard Puget Sound ADU inspection sequence applied: footing, underfloor MEP, framing, plumbing rough, electrical rough, mechanical rough, insulation, drywall nailing, shower pan, gas piping, final building, final plumbing, final electrical, final mechanical, and final energy verification (blower-door ≤3 ACH50). All passed with no notable callbacks — typical for our builds because we run internal QA checklists at each milestone.

    Go deeper: Issaquah ADU permit timeline

PROJECT_ISSAQUAH HILLSIDE DADU

Want a build like "Issaquah Hillside Dadu" on your lot? Get a real number.

We can share the exact scope, finishes and budget from this project — and tell you what the same build would cost on your address.

  • Same crews, same subs, same standards as "Issaquah Hillside Dadu"
  • Free build-like-this feasibility on your address
  • Reply within one business day
Replies within 1 business day
WA Lic. GOLDESA747LZBuilding since 2012
Direct line · Golden State ADU(425) 642-4142

We reply within 1 business day. No spam, ever.

◇ No sales script · No spam · Your details stay with our team