The full sequence in 12 honest steps — feasibility, design, 10–14 wk of permitting, foundation, framing, finish, and Certificate of Occupancy. Roughly 10 months end-to-end at $442k all-in for a typical Redmond 800 sqft DADU.

The 12 steps, in order

  1. STEP_01

    1wk

    Feasibility & site analysis

    We pull the Redmond parcel report, GIS overlays, and R-4 through R-8 code to confirm setbacks, lot coverage, height limits, and any ECA/critical-area triggers. Outcome: a 1-page go/no-go with maximum buildable envelope on your Redmond lot.

  2. STEP_02

    3wk

    Schematic design & client review

    Two to three floor-plan options sized to your goals (rental income, multi-gen, home office). We pair each with an exterior massing and a target budget anchored to Redmond's current trade-bid environment.

  3. STEP_03

    4wk

    Construction documents & engineering

    Structural, MEP, energy-code (WSEC 2021), and any geotech reports required for Redmond (tree retention: 35% canopy retention required — redmond is the strictest in king county). Stamped CDs are what gets submitted, not preliminary plans.

  4. STEP_04

    12wk

    Redmond permit submittal & review

    Intake with Redmond permitting, response to correction cycles, and any required side-sewer / right-of-way / tree-protection sub-permits. Redmond currently averages 10–14 wk on ADU review.

  5. STEP_05

    2wk

    Mobilization & site work

    Erosion control, tree-protection fencing, demolition (if any), excavation, utility trenching. 5,000 sqft lot minimum applies for new DADUs.

  6. STEP_06

    2wk

    Foundation

    Forms, rebar, inspection, pour, cure. Stem-wall or slab-on-grade per the soils report. Standard spread footings work on most lots.

  7. STEP_07

    4wk

    Framing, roof & weather-in

    Floor, walls, roof, sheathing, windows, and dried-in envelope. From here the structure is protected from Puget Sound weather and trades can sequence in parallel.

  8. STEP_08

    3wk

    Rough MEP & inspections

    Plumbing, electrical, HVAC (typically heat-pump mini-split for Redmond), low-voltage. Each scope passes its rough-in inspection before insulation.

  9. STEP_09

    4wk

    Insulation, drywall & exterior

    WSEC-compliant insulation, vapor control, drywall hang/finish, siding (Hardie/wood/metal), and roofing. Exterior finish locks down the envelope's long-term durability.

  10. STEP_10

    4wk

    Interior finish, fixtures & cabinets

    Flooring, paint, doors, trim, cabinets, counters, plumbing fixtures, light fixtures, appliances. Where most of the "luxury feel" budget actually shows up.

  11. STEP_11

    1wk

    Final inspections & Certificate of Occupancy

    Redmond final building, electrical, mechanical, plumbing inspections; energy-code verification; address assignment; CofO issued. Once issued, the unit can legally be occupied or rented.

  12. STEP_12

    2wk

    Punch list, warranty & lease-up

    30/60/90-day touch-ups. We hand over a warranty binder (manuals, model numbers, Golden State ADU Builders Inc 2-year workmanship, 10-year structural). If renting, we provide Redmond comparable rent data for the listing.

FAQ

Building an ADU in Redmond — straight answers

  • How long does it take to build an ADU in Redmond?

    Roughly 10 months end-to-end on a typical Redmond lot — about 12 weeks of permitting (Redmond currently averages 10–14 wk) plus 30 weeks of design, site work, framing, and finish. Lots with ECA, geotech, or shoreline overlays add 4–8 weeks.

    Go deeper: Redmond ADU overview

  • What does an 800 sqft DADU cost in Redmond?

    Around $442k all-in for a mid-spec 800 sqft detached ADU in Redmond — design, permits, construction, utility connections. Garage conversions run 35–45% lower, attached ADUs (AADU) about 10–15% lower.

    Go deeper: Redmond ADU cost breakdown

  • Do I need an architect, a designer, or just a contractor in Redmond?

    Most Redmond ADUs under 1,000 sqft can be permitted with a stamped designer set; full architectural service is optional but valuable on tight or sloped lots. We carry both in-house, so the client doesn't pay for a coordination layer they don't need.

    Go deeper: Read the Eastside deck cost & permits: cedar, IPE, composite (2026) guide

  • Can I live in the main house while the ADU is being built in Redmond?

    Yes for detached ADUs (DADUs) — the main house stays habitable the entire build. Attached ADUs and garage conversions involve 2–6 weeks of louder/dustier work near the main house, but the main house remains occupiable throughout.

    Go deeper: Redmond ADU overview

  • What's the riskiest part of building an ADU in Redmond?

    Tree retention: 35% canopy retention required — Redmond is the strictest in King County — that's where Redmond projects most often slip schedule or pop the contingency. We sequence geotech, arborist, and side-sewer scope before permit submittal so surprises surface during design (cheap) rather than after foundation (expensive).

    Go deeper: Redmond ADU overview

  • What permits do I need to build an ADU in Redmond?

    Master Use Permit (where applicable), building permit, mechanical, plumbing, electrical, side-sewer connection, and any tree/right-of-way/shoreline sub-permits. Redmond permitting packages most of these under a single ADU intake.

    Go deeper: Redmond ADU permit timeline

CITY_DOSSIER / REDMOND· 47.6740°N 122.1215°W

Built in Redmond — what we know that the spec sheet won't tell you.

A live dossier from our field PMs: the permit counter, the soils, the bylaw that just changed, and the streets where ADUs are already cash-flowing.

Map · King CountyOpen ↗
Redmond
Drive-time from yard · ≈ 26 min via 520© OpenStreetMap contributors
Population78,213
Median lot7,800 sq ft
ADU permits / yr64 (2024)
Build cost band$330–380 / sq ft
Right now in Redmond
Air quality · US AQI
Source · Google Maps PlatformAffects pour windows + finish schedule
LIVE_INTEL / REDMOND · 6 SIGNALS
Pour-feasibility · todayLoading
/ 100 · Awaiting feed
  • Weather feed loading
Derived live · Redmond weather + AQI
Sun rhythm · RedmondDaylight
5:25 AM
9:05 PM
15h 40m daylight
Golden hour · 8:18 PM
98% of June peak
NOAA solar formulas · computed
Moon · cure-week planner
Loading

We track lunar weeks for slab pours — clear nights drop ambient temperature faster, which slows surface curing. Schedule wet slabs midweek under waxing light.

Conway approx · computed
Seismic · 24h within 60 miLoading
USGS earthquake.usgs.gov
On-site clock · Redmond
—:—
· Pacific

Loading. Our standard crew window is 7:00–17:00 weekdays — noise ordinances in most Puget Sound cities allow exterior power tools only inside that band.

America/Los_Angeles · live
Build-rules pulseWithin window
7:00–17:00
Power-tool window · Mon–Fri
ADU permits YTD pace

Sunday exterior work is restricted in most Puget Sound jurisdictions. We sequence interior trades around it.

Redmond municipal code · annualized
SPEC_02 / CITY_INTEL

Environmental & locational intelligence

03 / SOLAR_POTENTIAL

Rooftop solar at this address

04 / POLLEN_FORECAST

Tree · Grass · Weed (3-day)

05 / WALK_SCORE

0.5-mile amenity density

06 / NWS_ALERTS

Active NWS weather alerts

LOCATIONAL_INTEL / REDMOND
Drive times from RedmondLoading

Calculating live drive times to four metro anchors…

Real commute time matters for ADU rent comps — and for our crews. We keep installs within a 60-minute radius of our Puget Sound yard.

Data provenance

Drive times pulled live from the Google Routes API (traffic-aware matrix). Each request is timestamped so you can see exactly when the numbers were last refreshed — no stale brochure data.

Google Routes API · traffic-aware
Street view · RedmondLive imagery
Recent Google Street View imagery centered near Redmond

Lot context matters as much as zoning. We pre-screen access, slope, and tree canopy from imagery before scheduling the site visit.

Google Street View · proxied
Tidal window · RedmondLoading

Waterfront lots: shoreline excavation and barge access windows depend on these. We schedule pours away from extreme low tides when the soils dry unevenly.

NOAA · — mi away
Recent permits · RedmondLoading

Open-data signal of nearby construction velocity — useful for ADU comps and for anticipating examiner workload.

data.seattle.gov · ~3 mi radius
Permit counter · Redmond
Redmond Planning & Community Development
15670 NE 85th St, Redmond 98052
Mon–Fri 8a–5p · digital pre-app required
Local zoning quirk

Education Hill & Grass Lawn lots often hit tree-retention thresholds before FAR — plan crown protection early.

Sourced from Golden State ADU field PMs · WA Lic. GOLDESA747LZ
Best build window
May → October

Bar shows pour-friendly months · dot marks the current month.

  • Seismic
    SDC D · stable plateau geology
  • Soil
    Glacial till on plateau, peat pockets near Sammamish River
  • Climate
    Slightly drier than Seattle (≈34″/yr), east-of-lake sun bonus
  • Topography
    Mostly gentle slope
  • HOA prevalence
    ≈ 28% — Education Hill, Grass Lawn, Idylwood
Transit signal
2 Line Downtown Redmond + Marymoor Village stations (2024)

Station-area lots earn the largest rent premium in this market.

School signal
Lake Washington School District

Rental yield estimate: $2,900–3,700 / mo · Microsoft proximity drives demand

Local incentive

Tech-corridor zoning allows live/work ADU configurations near Overlake

Hidden gem

Tree-retained DADUs in Education Hill pre-lease in <14 days.

Build cost · Redmond vs Puget Sound
+$30 vs regional median
$250 / sqftRedmond$355$425 / sqft
Other cities we hold a permit history in
PLAYBOOK_REDMOND / FREE

Skip 90 hours of Redmond research — get the playbook we run our builds from.

The article gets you 70% of the way. The other 30% is lot-specific. Send the address and we send a customized version of the playbook for your build.

  • Redmond-specific permit + zoning callouts
  • Vendor list (geotech, arborist, surveyor) we trust locally
  • Free, ~12-page PDF returned within 48h
Replies within 1 business day
WA Lic. GOLDESA747LZBuilding since 2012
Direct line · Golden State ADU(425) 642-4142

We reply within 1 business day. No spam, ever.

◇ No sales script · No spam · Your details stay with our team