Skip to main content

CAP_15 / HOW-TO / LAKEWOOD

How to build an ADU in Lakewood, WA

The full sequence in 12 honest steps — feasibility, design, 8–12 wk of permitting, foundation, framing, finish, and Certificate of Occupancy. Roughly 9 months end-to-end at $357k all-in for a typical Lakewood 800 sqft DADU.

The 12 steps, in order

  1. STEP_01

    1wk

    Feasibility & site analysis

    We pull the Lakewood parcel report, GIS overlays, and R-1 / R-2 / R-3 / R-4 code to confirm setbacks, lot coverage, height limits, and any ECA/critical-area triggers. Outcome: a 1-page go/no-go with maximum buildable envelope on your Lakewood lot.

  2. STEP_02

    3wk

    Schematic design & client review

    Two to three floor-plan options sized to your goals (rental income, multi-gen, home office). We pair each with an exterior massing and a target budget anchored to Lakewood's current trade-bid environment.

  3. STEP_03

    4wk

    Construction documents & engineering

    Structural, MEP, energy-code (WSEC 2021), and any geotech reports required for Lakewood (american lake and steilacoom lake shoreline jurisdictions). Stamped CDs are what gets submitted, not preliminary plans.

  4. STEP_04

    10wk

    Lakewood permit submittal & review

    Intake with Lakewood permitting, response to correction cycles, and any required side-sewer / right-of-way / tree-protection sub-permits. Lakewood currently averages 8–12 wk on ADU review.

  5. STEP_05

    2wk

    Mobilization & site work

    Erosion control, tree-protection fencing, demolition (if any), excavation, utility trenching. 6,000 sqft lot minimum applies for new DADUs.

  6. STEP_06

    2wk

    Foundation

    Forms, rebar, inspection, pour, cure. Stem-wall or slab-on-grade per the soils report. Standard spread footings work on most lots.

  7. STEP_07

    4wk

    Framing, roof & weather-in

    Floor, walls, roof, sheathing, windows, and dried-in envelope. From here the structure is protected from Puget Sound weather and trades can sequence in parallel.

  8. STEP_08

    3wk

    Rough MEP & inspections

    Plumbing, electrical, HVAC (typically heat-pump mini-split for Lakewood), low-voltage. Each scope passes its rough-in inspection before insulation.

  9. STEP_09

    4wk

    Insulation, drywall & exterior

    WSEC-compliant insulation, vapor control, drywall hang/finish, siding (Hardie/wood/metal), and roofing. Exterior finish locks down the envelope's long-term durability.

  10. STEP_10

    4wk

    Interior finish, fixtures & cabinets

    Flooring, paint, doors, trim, cabinets, counters, plumbing fixtures, light fixtures, appliances. Where most of the "luxury feel" budget actually shows up.

  11. STEP_11

    1wk

    Final inspections & Certificate of Occupancy

    Lakewood final building, electrical, mechanical, plumbing inspections; energy-code verification; address assignment; CofO issued. Once issued, the unit can legally be occupied or rented.

  12. STEP_12

    2wk

    Punch list, warranty & lease-up

    30/60/90-day touch-ups. We hand over a warranty binder (manuals, model numbers, Golden State ADU Builders Inc 2-year workmanship, 10-year structural). If renting, we provide Lakewood comparable rent data for the listing.

FAQ

Building an ADU in Lakewood — straight answers

  • How long does it take to build an ADU in Lakewood?

    Roughly 9 months end-to-end on a typical Lakewood lot — about 10 weeks of permitting (Lakewood currently averages 8–12 wk) plus 30 weeks of design, site work, framing, and finish. Lots with ECA, geotech, or shoreline overlays add 4–8 weeks.

  • What does an 800 sqft DADU cost in Lakewood?

    Around $357k all-in for a mid-spec 800 sqft detached ADU in Lakewood — design, permits, construction, utility connections. Garage conversions run 35–45% lower, attached ADUs (AADU) about 10–15% lower.

  • Do I need an architect, a designer, or just a contractor in Lakewood?

    Most Lakewood ADUs under 1,000 sqft can be permitted with a stamped designer set; full architectural service is optional but valuable on tight or sloped lots. We carry both in-house, so the client doesn't pay for a coordination layer they don't need.

  • Can I live in the main house while the ADU is being built in Lakewood?

    Yes for detached ADUs (DADUs) — the main house stays habitable the entire build. Attached ADUs and garage conversions involve 2–6 weeks of louder/dustier work near the main house, but the main house remains occupiable throughout.

  • What's the riskiest part of building an ADU in Lakewood?

    American Lake and Steilacoom Lake shoreline jurisdictions — that's where Lakewood projects most often slip schedule or pop the contingency. We sequence geotech, arborist, and side-sewer scope before permit submittal so surprises surface during design (cheap) rather than after foundation (expensive).

  • What permits do I need to build an ADU in Lakewood?

    Master Use Permit (where applicable), building permit, mechanical, plumbing, electrical, side-sewer connection, and any tree/right-of-way/shoreline sub-permits. Lakewood permitting packages most of these under a single ADU intake.